| Client |
NTPC Limited (Government of India), World’s 5th Largest Energy Company |
| Project |
800 MW Hydro Power Project |
| Location |
Located around 150 Kms. From Chandigarh in Northern India. |
| Period of Completion |
46 months |
| Scope |
Work involves Designing, Details Engineering, Manufacturing, Transportation, Installation and
Commission of all hydro-mechanical equipment.
World's largest Vertical Lift Gates for Diversion Tunnels measuring 6.5 M (Width) x 14 M (Height) with
acting water head of 115 M operated using 700 mm Dia, 17 M long & 800 MT capacity hydraulic hoist.
Spillway Radial Crest gates of size 17.1 M (Width) x 17.74 M (Height) making it one of the largest Radial gates in the world.
Radial gates consist of a flap gates of size 14M (Width) x 3M (Height). |
| Challengers & Achievements |
First of its kind, size & Capacity installed in India.
Design of gates was very complicated without any precedence in India.
Installation & commissioning work of the world's largest Vertical lift gates completed in record time of 2 months. |
| Total Tonnage |
1000 MT |